Notice of Access ramp construction work at Mandeville Road
Work item: HS2-MW-SCS-Ph1-Ar-So-S2-Ex-Mat-35-13/01/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Construction, Excavation works
- Estimated Start Date
- 31/01/2022
- Estimated End Date
- 13/05/2022
What we are doing
What we are doing
From 31 January to 13 May 2022, we will be constructing the access ramp and lower piling platform at the foot of the railway embankment in preparation for excavation of the vent shafts in the area shown on the map overleaf.
We will be excavating the area behind the sheet piles and creating an access ramp from our site entrance down to the foot of the embankment. Once this ramp is in place, we will construct the lower piling platform.
We will use one excavator, a bulldozer and a roller to compact the ground.
How these works might affect you
You may experience increased construction noise during this period. Noise and vibration monitoring will be in place throughout these works. Lorry movements in and out of site will increase as we take away the soil we have removed from the embankment.
We will use water sprays to reduce dust generated by construction activities.
We would like to apologise in advance for the disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.