Notice of additional weekend deliveries to our Willesden Euroterminal site
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Ex-mat-1-05/01/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Willesden Euroterminal
- Worksite Name
- Willesden Euroterminal site
- Contractor
- SCS JV
- Type of works
- Excavated material deliveries
- Estimated Start Date
- 07/01/2023
- Estimated End Date
- 31/03/2023
What we are doing
Weekend excavated material deliveries to Willesden Euroterminal site
We will be carrying out additional excavated material deliveries to our Willesden Euroterminal site to support the tunnel boring activity taking place at our site in West Ruislip. The excavated materials will be removed from the Willesden Euroterminal site by rail and will be transported to locations in Cambridge, Kent, and Bedfordshire.
This activity will require lorry access to the Willesden Euroterminal site through our Channel Gate Road entrance on Saturdays and Sundays from 7 January.
To minimise lorry movements along Channel Gate Road to 1-way, we will be utilising our canal crossing bridge. The activities that will be taking place on our site will consist of tipping lorries and managing loads using a loading shovel and excavator.
Our working times will be from 8am to 6pm and we will follow best practice methodology as outlined in the Code of Construction Practice (CoCP). We use wheel washers on our sites to mitigate dirt being transported by our lorries and road sweepers on our lorry routes.
The delivery of material is expected continue until the end of March 2023.
Dates and times mentioned in this notification may change – we will provide updates at https://www.hs2.org.uk/in-your-area/map/