Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog works-1-27/06/2022

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Adelaide Road, Eton Road
Worksite Name
Adelaide Road
Contractor
National Grid, SCS JV
Type of works
Utility works / surveys
Estimated Start Date
11/07/2022
Estimated End Date
31/10/2022

What we are doing

As the construction of the Adelaide Road Ventilation Shaft continues, below is a summary of the works that will take place over the coming months.

National Grid works.

From 11 July to 22 July 2022 National Grid will carry out works to protect cables underneath Adelaide Road. The works will take place within the HS2 site, and within the current lane closure.

This will be followed by additional works being completed 20m west of this site between 25 July to 19 August 2022. The additional work will be located on either side of the road and the pavement outside Adelaide Medical Centre.

Sewer works underneath Adelaide Road and Eton Road

From 25 July to 26 August 2022 we will be carrying out works on the main sewer located underneath Adelaide Road and Eton Road. The purpose of the utility works is to strengthen the existing sewer pipe by installing a sewer liner which will protect the main sewer while we build HS2 tunnels in the London Borough of Camden. We will do this by digging into the ground to create a trench which will be at the depth of the main sewer pipe underneath Adelaide Road. Once complete, we will carry out the installation of a liner inside the sewer.

We will have a road closure in place at the junction of Eton Road and Adelaide Road between 25 July and 19 August 2022.
From 22 to 26 August 2022, Adelaide Road will reopen but the road closure will remain in place on Eton Road.

Clearly signed traffic, cycle and pedestrian diversion routes will be in place for the duration of these works.
Your utility services will not be affected during these works and we will use noise reducing barriers where possible.

Ground anchors update
The start date for the installation of ground anchors at Adelaide Road has changed since we last notified you. The works will now start in August 2022, for up to 19 weeks. We will provide further update in due course.

Additional utility works from late August 2022
Further utility works will take place on Adelaide Road from 29 August until late October. Lane closures will be required. Further information will be provided nearer the time.

For details of above works please see notification below.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]