Updated notice of Aston Church Road utility works

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-37-29/11/2022

Work Item Summary

Project Phase
Phase 1
Region
Birmingham, West Midlands
Location
Nechells
Worksite Name
Aston Church Road
Contractor
BBV JV
Type of works
Footpath diversion, Lane closure
Estimated Start Date
25/02/2023
Estimated End Date
27/02/2023

What we are doing

Updated notice – the dates for the work have changed and will now take place on 25 February to 27 February 2023 for two nights.

We have been working on some utility diversions along the footpath and embankment at the junction of Aston Church Road and Heartlands Parkway. We now need to erect a sign and carry out some minor works in the area. These works will be carried out between on 9 January 2023 to 13 January 2023 between 8am – 5pm.
There will be a lane closure at the junction of Aston Church Road and Heartlands Parkway as well as a closure of a section of the south footway. Traffic management will be in place to allow us to work safely.

Download information relating to these works