Notice of Balfour Beatty VINCI works on Network Rail asset
Work item: HS2-EW-BBV-Ph1-Ar-No-N2-Prog-works-12-30/07/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Lea Marston
- Contractor
- BBVS JV
- Type of works
- Enabling works
- Estimated Start Date
- 14/08/2021
- Estimated End Date
- 05/09/2021
What we are doing
In early 2021, Balfour Beatty VINCI sent out a notification to outline works we were completing on the Network Rail track to install lineside protection. This lineside protection enables us to create a safe environment for our construction workers and users of the existing rail network, whilst we construct HS2.
The second phase of this work is now due to commence, starting Saturday 14 August. We will then continue working for three weekends up until 5 September.
To complete this work, we will enter the working area through the existing Network Rail access point close to Lea Marston. We will also utilise an access gate at Newlands Farm, however this will only be used by passenger vehicles.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]