UPDATE Notice of Blackgrove Road North Traffic Management

Work item: HS2-EKFB-25-1057

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Waddesdon
Worksite Name
Blackgrove Road
Contractor
EKFB JV
Type of works
Traffic management
Estimated Start Date
16/06/2025
Estimated End Date
04/07/2025

What we are doing

From 16 June to 4 July, we will be working along Blackgrove Road (North). This will be to install hard standing for a permanent power supply to an existing lighting column on the Blackgrove Road roundabout.

While we carry out this work, there will be a lane closure in place on Blackgrove Road managed by 2 -way traffic lights set up from 8:30am to 5:30pm, weekdays only (Monday to Friday). At weekends, the traffic lights will be removed.

Please note, these dates may be subject to change due to circumstances outside of our control.