Notice of boundary wall vegetation clearance

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-22-20/07/2022

Work Item Summary

Project Phase
Phase 1
Location
Washwood Heath
Contractor
BBV JV
Type of works
Vegetation clearance
Estimated Start Date
15/08/2022
Estimated End Date
18/08/2022

What we are doing

Vegetation clearance Drews Lane

We will be removing the remaining vegetation on Drews Lane. The work will consist of strimming and tidying the overgrowth next to our fencing.

What we will be doing?

Vegetation around and on the side of the pavement will be cleared using handheld cutters and strimmers. We will put in place barriers around our working area but the footpath will remain open. It is anticipated that there may be limited noise from the brush cutters, although this will be kept to a minimum.

We plan to carry out this work during the week commencing Monday 15 August. We expect this work to be completed in three days.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]