Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-3-19/06/2021

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Greenford
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
05/07/2021
Estimated End Date
10/07/2021

What we are doing

Bridge surveys in July 2021
During July, our surveying team will be visiting railway bridges on Greenford Road, Horsenden Road and Alperton Lane to carry out surveys overnight. We’ll also visit the West Gate underbridge at Hanger Lane roundabout. The surveys will help to inform our design decisions in the area.

We will take pictures and investigate the condition of the bridges using a mobile tower and ladders. The surveys should not cause any disruption.

Due to the location of the surveys, temporary traffic management will be in place to ensure the activity can be carried out safely.

Survey dates
The surveys are planned on the following dates:
• Lyon Way – 5 July to 7 July
• Alperton Lane – 6 and 7 July
• Greenford Road – 7 and 8 July
• Horsenden Road South – 8 and 9 July
• West Gate underbridge, Hanger Lane roundabout – 9 and 10 July

Maps showing the survey locations are included on the following pages.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]