Notice of CCTV surveys at Carr Road, Cherry Gardens and Northolt Industrial Estate
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-7-23/04/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Carr Road, Northolt
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 12/05/2021
- Estimated End Date
- 18/05/2021
What we are doing
What we are doing
From 12 to 18 May 2021, we will be carrying out utility surveys at Carr Road, Cherry Gardens and Northolt Industrial Estate, shown on the maps overleaf. The surveys will provide us with information on the condition and location of the utility services and help us to decide how best to protect them while we are building HS2.
We will investigate the condition of the sewer system using a CCTV camera mounted on a small robot. Should we find a blockage we may need to flush the system using a high-pressure water jet in order to carry out the investigation.
How the surveys might affect you Temporary traffic management and a lane closure will be in place to ensure the surveys can be carried out safely.
Your utility services will not be affected.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]