Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-CR-43-09/05/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak Common, Old Oak Common lane
- Worksite Name
- Old Oak Common
- Contractor
- BBVS JV
- Type of works
- Brickwork repair, Bridge protection works, Cable works
- Estimated Start Date
- 15/08/2024
- Estimated End Date
- 31/08/2024
What we are doing
As we continue with the works at Old Oak Common Station, we need to complete asset protection works near to the central line railway.
The works involve installing protection to existing cable management systems adjacent to the track, undertaking surveys and repairs to existing bridge abutment brickwork and the removal of redundant services.
Works will occur on intermittent nights between Thursday 15 August and Saturday 31 August 2024 between 01:00 and 05:30. The work needs to take place at night as we need to access the Central line during off-peak hours; the safest option is to do this at night.
Please see the link below for further information.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]