Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-CR-43-09/05/2024

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak Common, Old Oak Common lane
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Brickwork repair, Bridge protection works, Cable works
Estimated Start Date
15/08/2024
Estimated End Date
31/08/2024

What we are doing

As we continue with the works at Old Oak Common Station, we need to complete asset protection works near to the central line railway.

The works involve installing protection to existing cable management systems adjacent to the track, undertaking surveys and repairs to existing bridge abutment brickwork and the removal of redundant services.

Works will occur on intermittent nights between Thursday 15 August and Saturday 31 August 2024 between 01:00 and 05:30. The work needs to take place at night as we need to access the Central line during off-peak hours; the safest option is to do this at night.

Please see the link below for further information.

Download information relating to these works