Notice of closure A4010 Risborough Road

Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-50-12/03/2024 1MC12-EKF-IN-NTE-CS04-000084

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A4010 Risborough Road, Aylesbury
Contractor
EKFB JV
Type of works
Road closure, Vegetation maintenance
Estimated Start Date
02/04/2024
Estimated End Date
05/04/2024

What we are doing

In April, we will be completing de-vegetation around the new Stoke Mandeville relief road at the point that it will connect with the existing carriageway.

This will involve felling works to where it has been established that some root protection zones will be compromised due to proximity to our construction, therefore a small number of trees will need to be removed.

To carry out these works we will be closing a section of the road with a signed diversion route. This is for safety reasons as our operatives will be working in and around the carriageway.

To reduce impact on road users, the road closure will be in operation during off-peak times.

When will these works take place?

  • Tuesday 2 April – Friday 5 April (9:00am – 3:00pm)

These dates may change due to conditions outside of our control but we will endeavour to complete them in or around the dates suggested above.

 