Notice of closure, Helmdon Road, Greatworth and footpath AN13

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-23-15/08/2023

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire
Location
Greatworth
Contractor
EKFB JV
Type of works
Footpath closures, Footpath diversion, Road closure
Estimated Start Date
02/10/2023
Estimated End Date
31/12/2025

What we are doing

To construct the Greatworth Green Tunnel we will be closing a section of Helmdon Road, Greatworth.

  • Helmdon Road will be closed from 2 October 2023 until the
    completion of the Greatworth Green Tunnel and road
    realignment at the end of 2025.
  • Traffic lights on the B4525 from 2 to 14 October 2023.
  •  PRoW footpath AN13 will close from 2 October until the
    completion of the Greatworth Green Tunnel at the end of 2025.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]