Notice of closure of Bangley Lane

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-9-07/12/2023

Work Item Summary

Project Phase
Phase 1
Region
Staffordshire, West Midlands
Location
Bangley
Contractor
BBV JV
Type of works
Road closure, Utility works / surveys
Estimated Start Date
28/05/2024
Estimated End Date
10/06/2024

What we are doing

We will be undertaking utilities surveys on Bangley Lane that will require a full two-week closure.  This will be to establish what utilities are beneath the road and what condition they are in ahead of future construction works. To complete these works safely we will need to implement a safe working area that will require the full closure of Bangley Lane.

We will install a full closure on Bangley Lane to complete utilities surveys as follows:

  • 28 May to 10 June 2024 24 hours per day (Including weekends). Our working hours will be 8.00am to 6.00pm and if required 8.00am to 1.00pm Saturday.

Access will be maintained for pedestrians, cyclists, and equestrians from either end of Bangley Lane.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]