Notice of closure of M42 Junction 9 hard shoulder

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-07-14/05/2024

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Kingsbury
Contractor
BBV JV
Type of works
Hard Shoulder closure
Estimated Start Date
02/09/2024
Estimated End Date
13/09/2024

What we are doing

We have recently constructed the new Marston Box structure, a bridge that will take the HS2 line over the M42 motorway just north of Junction 9. We have further works to undertake on the bridge in order to complete the installation of the parapets.
To do this work safely we will need to close the hard shoulder of the M42 in both directions.

We will carry out these works from Monday 2 September until Friday 13 September. The hard shoulder closure will remain in place 24 hours a day during this period.