Notice of Closure of Public Rights of Way, QUA/36/1 and QUA/37/1, Calvert

Work item: HS2-EKFB-25-1403

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Worksite Name
PRoW QUA/36/1
Contractor
EKFB JV
Type of works
PRoW Closure
Estimated Start Date
06/10/2025
Estimated End Date
31/05/2026

What we are doing

As part of our preparatory works and for the safety of the public, we have previously closed some Public Rights of Way (PRoW) in the Calvert area.

The currently closed QUA/36/1, which is located to the west of Finemere woods, requires an extension in length to facilitate the construction of drainage systems and associated pipework.

A section of the footpath, QUA/37/1, which connects to QUA/36/1 from the south, also requires a temporary closure. This is necessary to provide the team with a safe working area to demolish the existing bridge, GUA1, and complete essential drainage works. The map overleaf shows the location of these footpaths.

This section of Public Rights of Way known as QUA/36/1 and QUA/37/1,will be closed from 6 October 2025 – 31 May 2026.