Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Hams Hall
- Contractor
- BBV JV
- Type of works
- Lane closure
- Estimated Start Date
- 20/10/2025
- Estimated End Date
- 05/12/2025
What we are doing
We will be undertaking lane closures on Hams Lane, Coleshill over a 5-week period, using two separate phases, to carry out the civils works identified as part of “M16 shared accommodation track”.
These works will be along the west verge of Hams Lane and will consist of clearing vegetation and utility trial holes.
These single lane and full closures will be implemented from 9.30am-4.30pm each weekday over the following period:
· Monday 20 October 2025 to Friday 14 November 2025 (two-way traffic lights) (not including weekends)
· Monday 24 November 2025 to Friday 28 November 2025 (two-way traffic lights)
· Monday 1 December 2025 to Friday 5 December 2025 (two-way traffic lights)
Please note that we have planned the single lane closures on Hams Lane, Coleshill to avoid peak traffic flow periods.