Notice of construction of West Portal – Washwood Heath

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-50-04/11/2021

Work Item Summary

Project Phase
Phase 1
Region
Birmingham, West Midlands
Location
Washwood Heath
Worksite Name
Washwood Heath
Contractor
BBV JV
Type of works
Cement pours
Estimated Start Date
22/11/2021
Estimated End Date
31/01/2023

What we are doing

We will start constructing the diaphragm wall that will support the Bromford Tunnel West Portal on 22 November 2021. This work is expected to continue for a period of 14 months. The Tunnel Portal will be an entry and exit point to the tunnel for the new HS2 trains.

How we will construct the diaphragm wall

The diaphragm wall will be constructed by excavating the ground with large
machinery in a series of sections. Each section will be stabilised with a
specialised fluid to support the ground before it is then filled with concrete.

What to expect

• We will be using large machinery to excavate

• Our bentonite plant will be operational to produce the specialised
stabilising fluid. Bentonite is a natural occurring material that will be
mixed with water to produce a clay that helps to support the
ground as we excavate

• On some occasions we may need to work outside of core hours to
complete concrete pours.

 

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]