View route map
Notice of construction work, A423, Southam
Work item: HS2-MW-EK-Ph1-Ar-Ce-C3-Traf-41-10/10/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Worksite Name
- A423
- Contractor
- EKFB JV
- Type of works
- Construction
- Estimated Start Date
- 04/11/2024
- Estimated End Date
- 06/11/2024
What we are doing
As part of the for the construction of the A423 overbridge, EKFB are building new drainage culverts near the highway and installing a support method called sheet piling. This involves driving interlocking metal sheets into the ground, to create a strong retaining wall between the structure and the highway.
Works will be taking place by the A423 from Monday 4 November to Wednesday 6 November 2024.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]