Notice of continuing works on Hampstead Road

Work item: HS2-MW-MD-Ph1-Ar-So-S1-Traf-37-25/07/2024

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden
Worksite Name
Euston Station
Contractor
Mace Dragados JV
Type of works
Lane closure, Traffic management, Utility works / surveys
Estimated Start Date
22/04/2024
Estimated End Date
20/09/2024

What we are doing

Ongoing Thames Water works on Hampstead Road

We wrote to you in April 2024 (reference: HS2-MW-SCS-Ph1-Ar-So-S1-Traf-50-27/04/2023) to let you know that we are carrying out essential Thames Water connection works on Hampstead Road. These works were scheduled to be completed by 19 July 2024.

Due to challenges with the watermain connection these works will now be completed by mid-August 2024, earlier than scheduled. Works will take place Monday – Saturday, 8am – 5pm. During this extension, traffic management on Hampstead Road will remain in place. To ensure the safety of cyclists and how they interface with vehicles on Hampstead Road, Robert Street will remain temporarily closed until the works are completed.

You would have also received a notice from UKPN about their upcoming works on Hampstead Road and other surrounding roads. Please check this letter for further updates on works in the area, including traffic management, or please check here.

Please see the link below for further information.

Download information relating to these works