Notice of Crossrail Depot and utility protection slab works on Old Oak Common Lane
Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-prog-works-17-08/04/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak Common lane
- Worksite Name
- Old Oak Common
- Contractor
- BBVS JV
- Type of works
- Road closure
- Estimated Start Date
- 04/05/2022
- Estimated End Date
- 31/01/2023
What we are doing
Substation relocation and Crossrail Depot fence works
From Wednesday 4 May 2022 we will be moving an old substation, which is located opposite Kildun Court, further up Old Oak Common Lane near the Crossrail Depot.
This work requires a single lane road closure so excavation and piling can take place. The single lane road closure will start by Kildun Court and move up towards the Crossrail Depot as the works progress.
Work includes
- Rerouting the substation cables and replacing the fencing by the Crossrail Depot.
To support the work, we will be using large machinery and a crane. Lorries will be used to take away the excavated material.
These works are required to take place to prepare the area around Old Oak Common Station for future works. By ensuring the safe relocation of the substation and associated underground services that will be diverted to allow future tunnelling works at the site.
The work will take place up until January 2023, from 8am until 6pm Monday to Friday, 8am until 1pm on Saturdays. All noisy works will take place between 9am and 5pm.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]