Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-02-07/06/2024

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Worksite Name
Chetwode
Contractor
EKFB JV
Type of works
Road closure
Estimated Start Date
27/06/2024
Estimated End Date
01/07/2024

What we are doing

In late June, we will be removing some tree stumps along a section of School End. For reasons of safety, so we do not disturb utilities located below this area, the team will be using a vacuum excavator to slowly remove layers of soil and vegetation. A section of School End will be closed between 8.30am and 5.30pm on the following dates:
• Thursday 27 June
• Friday 28 June
• Monday 1 July