Skip to main page content
View route map

Notice of demolition of A47 Heartlands Parkway Bridge

Work item: HS2-EW-BBV-Ph1-Ar-No-N1-Prog-works-24-07/12/2021

Work Item Summary

Project Phase
Phase 1
Region
Birmingham, West Midlands
Location
Birmingham, Nechells, Saltley, Washwood Heath
Contractor
BBV JV
Type of works
Demolition works, Traffic management
Estimated Start Date
12/08/2021
Estimated End Date
06/09/2021

What we are doing

We will permanently close the bridge on 12 July to start preparation works and surveys. To be able to carry out these preparation works and surveys safely and effectively, we will need to put in place overnight lane closures on a section of A47 Heartlands Parkway.

There will be a lane closure in place from 13 to 16 August from 6.00pm to 5.00am. Access to properties and businesses will be maintained at all times.

Network Rail line closures

Following preparatory works the demolition of the bridge will take place over the following weekends
• 14-16 August,
• 21-23 August,
• 28-31 August (August Bank Holiday Weekend) and
• 4-6 September.

To allow us to work safely as we demolish the bridge, we will need to close a section of the Network Rail line. To minimise the time that we need to close the railway line our demolition works will be carried out 24 hours a day during the 4 weekends. For information about changes to train services during this period please visit www.nationalrail.co.uk.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]