Notice of demolition works – Wycombe Line wingwall (east)

Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-CR-34-24/02/2024

Work Item Summary

Project Phase
Phase 1
Location
Old Oak Common, Old Oak Common lane
Contractor
BBVS JV
Type of works
Demolition works, Utility works / surveys
Estimated Start Date
03/06/2024
Estimated End Date
07/06/2024

What we are doing

As we continue with the construction programme at Old Oak Common station site, we need to remove a Wycombe Line wingwall which is within the HS2 work site boundary and adjacent to Old Oak Common Lane.

The removal of the wingwall is required as part of the power cable diversion works, for details please follow this link.

The demolition of the Wycombe Line wingwall will take place between 8am and 5pm with an hour to set up and shut down on either side of these hours, from 3 June until 7 June 2024. The wingwall will be removed using handheld breakers, petrol saws and an excavator. To reduce the impact from these works we will use water to suppress dust and erect sound barriers and debris netting. We will not require any traffic management for this phase of the works.

For further details and location map please see the notification below.

Download information relating to these works