Notice of disruptive works near to Coleshill and Water Orton

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-52-21/05/2025

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Watton Lane
Worksite Name
Water Orton
Contractor
BBV JV
Type of works
Concrete pours
Estimated Start Date
14/06/2025
Estimated End Date
14/07/2025

What we are doing

BBV will be installing pre-cast concrete beams on the Watton House. Viaducts over the railway and carrying out key works on the structure including beam installation, steel fixing and concrete pouring. Unfortunately, these works cannot be undertaken during normal working hours without affecting the operation of the railway.

Works will be therefore be undertaken during a series of 41-hour closures of the railway over four weekends, starting at 8am on each Saturday and ending at 5am each Monday.

See breakdown below of the weekends impacted.

– Saturday 14 June to Monday 16 June
– Saturday 28 June to Monday 30 June
– Saturday 5 July to Monday 7 July
– Saturday 12 July to Monday 14 July

Download information relating to these works