Notice of drainage surveys in your local area

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Site-11-15/07/2021

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Adelaide Road
Worksite Name
Adelaide Road
Contractor
SCS JV
Type of works
Survey
Estimated Start Date
30/07/2021
Estimated End Date
20/08/2021

What we are doing

Drainage surveys planned in Sunny Mews
Our surveyors need to access a manhole in Sunny Mews to carry out a drainage survey. This will help us to understand how best to protect the drainage while we build HS2. To carry out the surveys, we will need to access the drainage via a manhole located in the parking area of Sunny Mews.

Survey visits planned on 30 July and 16-20 August
Our surveyors are planning to visit Sunny Mews on 30 July 2021 and between 16 and 20 August 2021 to carry out the surveys. On 30 July, they will visit to identify the specific location of the manhole. Between 16 and 20 August, we will visit to carry out the drainage survey. We will visit between 8am and 6pm. The dates for the surveys may change.

We will use a camera to investigate the condition of the drainage system and may need to flush the drains using a high-pressure water jet. Your utility services will not be affected during this time. You may receive further information from HS2 about this and we will write to you with more information soon.

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]