Notice of drainage surveys on Gloucester Avenue
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-12/10/21
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak
- Worksite Name
- Adelaide Road
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 08/11/2021
- Estimated End Date
- 25/11/2021
What we are doing
Drainage surveys planned from 8 November
On 8 to 25 November, we will be carrying out further drainage surveys on Gloucester Avenue and the surrounding roads. Most of the surveys are planned to take place overnight from 9pm to 6am. On 22 and 23 November are planned to take place during daytime working hours from 8am to 6pm. We will use a camera to investigate the condition of the drainage system and may need to flush the drains using a high-pressure water jet. Your utility services will not be affected, and noise levels will be kept to a minimum. We will use acoustic barriers, where possible.
How this might affect you
Temporary footpath closures and parking bay suspensions will be in place on the following roads:
• St Marks Crescent
• King Henry’s Road
• Regents Park Road
• Gloucester Avenue
• Princesses Road
• Edis Road
To minimise disruption, our surveying team are planning to carry out the drainage surveys in multiple phases.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]