Notice of Drainage work on the B4118, Birmingham Road
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-10-23/04/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- B4118
- Worksite Name
- B4118 Birmingham Road
- Contractor
- National Grid Electricity Distribution (NGED)
- Type of works
- Survey
- Estimated Start Date
- 13/05/2025
- Estimated End Date
- 23/05/2025
What we are doing
To complete construction of new 132kV Substation (Bromford BSP) National Grid Electricity Distribution (NGED) have installed a drain to serve the facility, for removal of excess rainwater.
For the drain to be fully adopted and maintained by Severn Trent Water (STW), a full survey and some remedial works are required to be carried out.
To improve traffic flow, we have divided the area into seven shorter sections on the B4118. NGED will have a specialist team working one section at a time (see detail on next page) completing one area before moving on to the next and working towards the Substation.
NGED will undertake the survey and remedial work over ten days between 13 May and 23 May 2025.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]