Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Drummond Street
- Contractor
- Mace Dragados JV
- Type of works
- Hoarding works
- Estimated Start Date
- 04/08/2025
- Estimated End Date
- 09/08/2025
What we are doing
To support gas replacement works starting Monday, 18 August 2025, the hoardings at the end of Drummond Street will be extended further into the road.
Key Details:
• Hoarding Move Date: Monday, 4 August 2025
• Time: Between 10:00 PM and 5:00 AM
• Duration: Up to 5 nights to complete
• Pedestrian Access: Will always be maintained to and from Euston Station
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]