Notice of early works from Chipping Warden to Wills Pastures
Work item: 1MC12-EKF-SE-NTE-CS10-000002
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Chipping Warden, Southam
- Contractor
- EKFB JV
- Type of works
- Early construction works, Utility works / surveys, Worksite / compound set-up
- Estimated Start Date
- 05/10/2020
- Estimated End Date
- 31/08/2021
What we are doing
We are undertaking early construction works to prepare the area for the HS2 route. This activity will include:
- Ground Investigation (GI) works
- Utility works including trial holes
- Localised clearance of vegetation and fencing
- Haul road, access roads and drainage activities
- Construction of a temporary bridge at Highfurlong Brook
When will these works take place?
We are looking to start these early works in October and continue until summer 2021. We will continue to keep you updated with further information as the works continue.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]