Notice of early works from Chipping Warden to Wills Pastures
Work item: 1MC12-EKF-SE-NTE-CS10-000002
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Chipping Warden
- Contractor
- EKFB JV
- Type of works
- Early construction works
- Estimated Start Date
- 01/10/2020
- Estimated End Date
- 31/08/2021
What we are doing
We are undertaking early construction works to prepare the area for the HS2 route. This activity will include:
- Ground Investigation (GI) works
- Utility works including trial holes
- Localised clearance of vegetation and fencing
- Haul road, access roads and drainage activities
- Construction of a temporary bridge at Highfurlong Brook
Download information relating to these works