Skip to main page content
View route map

Notice of Ellesborough Road lane closure for utility works – extension

Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-UT-33-28/02/2024 1MC12-EKF-IN-NTE-CS03-000111

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Wendover
Worksite Name
Buckinghamshire, Ellesborough Road
Contractor
EKFB JV
Type of works
Traffic management, Utility works / surveys
Estimated Start Date
31/05/2024
Estimated End Date
03/11/2024

What we are doing

In March, we completed our works for the new alignment of Ellesborough Road. We implemented traffic management due to the high voltage cable encased in concrete in the road. We are awaiting a date from one of our utility providers to remove the cable, and as a result we have had to extend our traffic management. When the utility provider confirms a date for removing the cable we will update and advise accordingly.

There are currently three-way traffic lights, 24 hours a day on Ellesborough Road. These will remain in place until our partner can move the cable and the concrete is removed.

Pedestrian and resident access is being maintained throughout this lane closure.

When will these works take place?
Traffic Management will remain in place until the removal of the cable is carried out by the utility provider.

 

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]