Notice of Ellesborough Road lane closure for utility works – extension
Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-UT-33-28/02/2024 1MC12-EKF-IN-NTE-CS03-000111
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Wendover
- Worksite Name
- Buckinghamshire, Ellesborough Road
- Contractor
- EKFB JV
- Type of works
- Traffic management, Utility works / surveys
- Estimated Start Date
- 31/05/2024
- Estimated End Date
- 03/11/2024
What we are doing
In March, we completed our works for the new alignment of Ellesborough Road. We implemented traffic management due to the high voltage cable encased in concrete in the road. We are awaiting a date from one of our utility providers to remove the cable, and as a result we have had to extend our traffic management. When the utility provider confirms a date for removing the cable we will update and advise accordingly.
There are currently three-way traffic lights, 24 hours a day on Ellesborough Road. These will remain in place until our partner can move the cable and the concrete is removed.
Pedestrian and resident access is being maintained throughout this lane closure.
When will these works take place?
Traffic Management will remain in place until the removal of the cable is carried out by the utility provider.
Download information relating to these works