Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-27-02/07/2024

Work Item Summary

Project Phase
Phase 1
Region
Birmingham, West Midlands
Location
Saltley
Contractor
BBV JV
Type of works
Footpath closures
Estimated Start Date
06/07/2024
Estimated End Date
07/07/2024

What we are doing

We need to carry out emergency works on a BT utility box located on Gate Street. To complete these repairs, we will be using light machinery along the footpath. We do not expect these works to cause high levels of noise or any impact to traffic. We will be carrying out the repairs from 6 July to 7 July 2024.

To enable us to carry out these works safely and effectively, we will need to put in place a temporary footpath diversion along a section of Gate Street that leads to Washwood Heath Road.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]