Notice of environmental work and temporary traffic lights on Uttoxeter Road, Blithbury
Work item: HS2-EW-BB-Ph2A-Prog-works-20-31/05/2022
Work Item Summary
- Project Phase
- Phase 2a
- Region
- Staffordshire
- Location
- Blithbury
- Worksite Name
- Blithbury
- Contractor
- Balfour Beatty
- Type of works
- Early Environmental Works
- Estimated Start Date
- 16/08/2022
- Estimated End Date
- 30/11/2022
What we are doing
We will be creating ecological mitigation ponds surrounded by grassland and woodland habitat creation on land to the north of Uttoxeter Road Bilthbury. We will use the ecological mitigation ponds to relocate any protected species such as great crested newts before we need to remove any other habitats.
Before we start to construct the ponds, we will improve the existing access off Uttoxeter Road by removing the existing vegetation at the
entrance and replacing it with ridged plastic mats. This is so we can bring large equipment on to the land to carry out the pond work. To do this safely, we will put two-way traffic lights in place along Uttoxeter Road.
We will put the temporary traffic lights in place for one day on Tuesday 16 August from 9am to 5pm.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]