Notice of environmental works on land off Checkley Lane, Wrinehill

Work item: HS2-EW-BB-Ph2A-Prog-works-9-31/05/2022

Work Item Summary

Project Phase
Phase 2a
Region
Cheshire
Location
Checkley Lane, Wrinehill
Worksite Name
Checkley Lane, Wrinehill.
Contractor
Balfour Beatty
Type of works
Early Environmental Works, Environmental mitigation works
Estimated Start Date
18/07/2022
Estimated End Date
31/05/2023

What we are doing

As part of our early environmental works, we will establish critical environmental and species relocation sites creating new habitats for local wildlife before any main work starts.

We will be creating ecological mitigation ponds surrounded by grassland habitat creation on land off Checkley Lane. We will use the ponds to relocate any protected species, such as Great Crested Newts before we need to remove any other habitats.

Before we start to construct the habitat areas, we need to excavate some archaeological trial trenches. These are to help us understand if there are any archaeological features or natural geological deposits that we need to be aware of before we start any other work. We will use a mechanical excavator to dig the trenches. No further excavation takes place at this stage.

When the work will take place

We will start the excavation work on 18 July 2022. We will begin work to create the ponds themselves once we have carried out the archaeological work, the pond work will be ongoing throughout the year. The timeline for the works is shown below:

  • Archaeological Trial Trenching – July ‘22 to August ‘22
  • Mitigation pond creation – August ’22 to October ‘22
  • Grassland creation – August ‘22 to September ‘22
  • Hedge planting – September ’22 to October ‘22
  • Bat house construction – March ’23 to May ‘23