Notice of environmental works on land off Moor Lane, Stockwell Heath

Work item: HS2-EW-BB-Ph2A-Prog-works-2-31/05/2022

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
Moor Lane, Stockwell Heath
Worksite Name
Moor Lane, Stockwell Heath
Contractor
Balfour Beatty
Type of works
Early Environmental Works, Environmental mitigation works
Estimated Start Date
24/06/2022
Estimated End Date
16/09/2022

What we are doing

We will be creating grassland and woodland habitats on land off Moor Lane. This is part of HS2’s plan to create a Green Corridor of richer, more diverse and better-connected landscapes along the railway. The Green Corridor is the largest single environmental project in the UK. Part of these works will also include the creation of hibernaculums and installation of bat and bird boxes. Hibernaculums are places where creatures, like reptiles seek refuge to keep themselves warm over the winter period.

Before we start to construct the habitat areas, we need to excavate some archaeological trial trenches. These are to help us understand if there are many archaeological features or natural geological deposits, that we need to be aware of before we start any other work. We will use a mechanical excavator to dig the trenches. No further excavation takes place at this stage.

When the work will take place

We will start the excavation work on 24 June 2022. We will begin the habitat creation works once we have carried out the archaeological work.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]