Notice of environmental works to land off Newlands Lane, Stockwell Heath

Work item: HS2-EW-BB-Ph2A-Prog-works-35-10/05/2022

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
Newlands Lane
Worksite Name
Stockwell Heath
Contractor
Balfour Beatty
Type of works
Environmental mitigation works
Estimated Start Date
30/05/2022
Estimated End Date
20/06/2022

What we are doing

We will be creating ecological mitigation ponds surrounded by grassland habitat creation on land off Newlands Lane, Stockwell Heath. We will use the ponds to relocate any protected species, such as Great Crested Newts before we need to remove any other habitats.

Before we start to construct the ponds, we need to excavate some archaeological trial trenches and pits. These are to help us understand if there are any archaeological features or natural geological deposits, that we need to be aware of before we start any other work. We will use a mechanical excavator to dig the trenches and pits.