Notice of environmental works to land south of Chorlton Lane, Chorlton

Work item: HS2-EW-BB-Ph2A-Prog-works-30-01/08/2022

Work Item Summary

Project Phase
Phase 2a
Region
Crewe
Location
Chorlton, Chorlton Lane
Worksite Name
Chorlton, Chorlton Lane
Contractor
Balfour Beatty
Type of works
Early Environmental Works, Environmental mitigation works
Estimated Start Date
05/09/2022
Estimated End Date
28/04/2023

What we are doing

As part of our early environmental works, we will establish critical environmental and species relocation sites creating new habitats for local wildlife before any main work starts.

We will be creating ecological mitigation ponds surrounded by grassland habitat creation on land to the south of Chorlton Lane. We will use the ponds to relocate any protected species, such as Great Crested Newts before we need to remove any other habitats.

Once this is complete, we will surround these ponds with grassland habitat. We will use the ponds to relocate any protected species, such as Great Crested Newts before we need to remove any other habitats. We will also install some new bird and bat boxes in the area to help the local wildlife.

When the work will take place

We will start the creation of the grassland habitat on 5 September 2022.

The timeline for the works is shown below:

  • Hedge and Woodland planting – September ‘22 to November ‘22
  • Bird and Bat box installation – September ’22 to November ‘22
  • Mitigation pond creation – September ’22 to March ‘23
  • Grassland creation – March ‘23 to April ‘23
  • Demobilisation – late-April ‘23