Notice of environmental works to land South of Den Lane, Wrinehill
Work item: HS2-EW-BB-Ph2A-Prog-works-4-16/08/2022
Work Item Summary
- Project Phase
- Phase 2a
- Region
- Crewe
- Location
- Den Lane, Wrinehill
- Worksite Name
- Den Lane, Wrinehill.
- Contractor
- Balfour Beatty
- Type of works
- Early Environmental Works, Environmental mitigation works
- Estimated Start Date
- 26/09/2022
- Estimated End Date
- 28/04/2023
What we are doing
As part of our early environmental works, we will establish critical environmental and species relocation sites creating new habitats for local wildlife before any main work starts.
We will be creating ecological mitigation ponds surrounded by grassland habitat creation on land to the south of Den Lane. We will use the ponds to relocate any protected species, such as Great Crested Newts before we need to remove any other habitats.
Before we start to construct the habitat areas, we need to excavate some archaeological trial trenches. These are to help us understand if there are any archaeological features or natural geological deposits that we need to be aware of before we start any other work. We will use a mechanical excavator to dig the trenches.
When the work will take place
We will start the work on 26 September 2022.
The timeline for the works is shown below:
- Archaeological trial trenching – September ‘22
- Hedge planting – September ‘22 to November ‘22
- Mitigation pond creation – September ’22 to March ‘23
- Grassland creation – March ‘23 to April ‘23
- Demobilisation – late-April ‘23
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]