Notice of extended hours working at EKFB Chipping Warden

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-12-12/03/2025

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire
Location
Chipping Warden
Worksite Name
Chipping Warden Green Tunnel
Contractor
EKFB JV
Type of works
Tunnel segment delivery
Estimated Start Date
01/04/2025
Estimated End Date
31/10/2025

What we are doing

As we continue to progress the Chipping Warden green tunnel we will be increasing our working hours. We have liaised with the local authority when planning this work and consent for the extended hours has been granted. Noise levels will be closely monitored to ensure they remain within the permitted limits and there will be regular reviews with the local authority.

Our additional working hours will include weekday night working, from 7am on Mondays to midnight on Fridays and at weekends from 7am to 6pm. From 1 April to 31 October 2025.