Notice of extended hours working at Lower Thorpe, Thorpe Mandeville

Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-32-24/01/2025

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire
Location
Thorpe Mandeville
Contractor
EKFB JV
Type of works
Extended working hours
Estimated Start Date
01/03/2025
Estimated End Date
31/10/2025

What we are doing

As we continue to progress the Lower Thorpe viaduct, we will be extending our working hours to include regular Sunday working.

During the additional day we will be focused in specific areas, undertaking activities related to the drainage culvers under and adjacent to the line of the railway.

Noise levels during this work will be closely monitored to ensure they remain within the permitted limits.

When will these works take place?

We will be working seven days a week in this location from 1 March until 31 October 2025, from 7am to 7pm.

Please see the link below for further information.