Notice of extended road closure – Chalfont St Giles
Work item: HS2-EW-Fusion -Ph1-Ar-Ce-C2-Traf-5-20/07/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Chalfont St Giles
- Contractor
- Align JV
- Type of works
- Road closure
- Estimated Start Date
- 04/08/2021
- Estimated End Date
- 28/02/2022
What we are doing
Widening works to the existing lane continue at Bottom House Farm Lane in Chalfont St Giles as this is the location of one of the Chiltern Tunnel’s ventilation shafts, until winter 2021.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]