Notice of extended working hours – Water Orton
Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Prog-works-23-04/11/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Birmingham Road
- Worksite Name
- B4118
- Contractor
- BBV JV
- Type of works
- Extended working hours, Worksite / compound set-up
- Estimated Start Date
- 04/04/2022
- Estimated End Date
- 31/12/2022
What we are doing
We are completing works in the compound area off the B4118
Birmingham Road by Water Orton. Our core working hours are 8.00am
– 6.00pm on weekdays and 8.00am – 1.00pm on Saturdays.
We delivered a notification in October outlining the extended working
hours we can utilise in areas of our compound. In order for us to
continue our working output to prepare for the tunnelling in this area,
we have consent approved to extend our working hours. This permits
us to work 24 hours a day from Monday to Friday, only in the tunnel
portal area of the site. There may be occasions where our workforce will
not have presence 24 hours a day on site. The welfare facilities in place
for the workforce are located near to the tunnel portal area and we will
position lighting to reduce impacts to local residents. Our extended
hours will begin from Monday 4 April, with this phase of work
continuing until the end of 2022.
All the other works in the area will still be subject to our core working
hours which are 8.00am – 6.00pm on weekdays and 8.00am – 1.00pm
on Saturdays.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]