Notice of fencing and archaeology works, Wendover
Work item: HS2-EW-Fusion-Ph1-Ar-Ce-C2-OTH-3-25/11/2020
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Wendover
- Contractor
- Fusion JV
- Type of works
- Archaeology, Early construction works
- Estimated Start Date
- 04/01/2021
- Estimated End Date
- 31/03/2021
What we are doing
As part of our continuing works ahead of the construction of the railway we need to undertake some further work in your area, these works will consist of:
- Boundary Fencing
- Localised vegetation clearance for fencing installation
- Archaeological test pit works
Boundary fencing
Our fencing works will continue in January 2021 and will be completed by the end of March 2021. For this stage of works we will not be closing any Public Rights of Way, but we will need to occasionally cross over them with machinery to access working areas.
To ensure this happens safely we will have marshals in place who will suspend pedestrian access temporarily while the machinery passes through. The fencing work will take place at multiple locations in the Wendover area. Please see the map enclosed in our works notification, available to view or download below.