Notice of fencing and archaeology works, Wendover

Work item: HS2-EW-Fusion-Ph1-Ar-Ce-C2-OTH-3-25/11/2020

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Wendover
Contractor
Fusion JV
Type of works
Archaeology, Early construction works
Estimated Start Date
04/01/2021
Estimated End Date
31/03/2021

What we are doing

As part of our continuing works ahead of the construction of the railway we need to undertake some further work in your area, these works will consist of:

  • Boundary Fencing
  • Localised vegetation clearance for fencing installation
  • Archaeological test pit works

Boundary fencing

Our fencing works will continue in January 2021 and will be completed by the end of March 2021. For this stage of works we will not be closing any Public Rights of Way, but we will need to occasionally cross over them with machinery to access working areas.

To ensure this happens safely we will have marshals in place who will suspend pedestrian access temporarily while the machinery passes through. The fencing work will take place at multiple locations in the Wendover area. Please see the map enclosed in our works notification, available to view or download below.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]