Notice of full weekend road closures, A43 and Radstone Road, Brackley

Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-42-07/09/2023

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire, Northamptonshire, Oxfordshire
Location
A43
Contractor
EKFB JV
Type of works
Road closure
Estimated Start Date
17/11/2023
Estimated End Date
11/12/2023

What we are doing

We are now ready to complete the tie in works that will join the new temporary road to the existing A43. These works will include the installation of drainage, lighting, signage, resurfacing and white lining. For reasons of safety, these works will require full weekend closures. These works are subject to consent

A section of the A43 Northbound, towards Northampton, will be fully closed, 24-hours a day, from 8pm Friday 8 December to 6am Monday 11 December. Once this work is completed, there will be a temporary diversion running alongside the existing A43 northbound for about a mile.

A section of the Radstone Road, also known as Whitfield Road, Radstone will also be fully closed during the full weekend closure detailed above. There will be no access from the Radstone Road junction onto the A43.