Notice of generator installation works, near B4118 Birmingham Road, Water Orton
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-2-21/11/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Water Orton
- Contractor
- BBV JV
- Type of works
- Construction, Worksite / compound set-up
- Estimated Start Date
- 04/01/2023
- Estimated End Date
- 31/12/2023
What we are doing
BBV have been mobilised in locations to the north of B4118 Birmingham Road since 2020. As part of our continued work in this location and to prepare for construction works in Water Orton, BBV will install generators to the north of the B4118 Birmingham Road.
These generators will temporarily power our construction activity in the area and will be in operation until the permanent power source is in place. The generators are planned to be in use until the end of 2023.
Download information relating to these works