Notice of GPR Surveys –A47, Mainstream Way and Arley Road
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-45-13/12/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham, West Midlands
- Location
- Birmingham
- Contractor
- BBV JV
- Type of works
- Ground investigations
- Estimated Start Date
- 13/12/2021
- Estimated End Date
- 16/12/2021
What we are doing
Upcoming Ground Penetrating Radar Surveys
We will be carrying out Ground Penetrating Radar (GPR) surveys in locations along Adderley Road and Adderley Gardens from Monday 13 December until Thursday 16 December. Dates are subject to the progress of the surveys programme.
GPR surveys are non-intrusive, they are completed using a machine which transmits an electromagnetic pulse into the ground. These pulses reflect off features in the ground, allowing us to identify the location and depth of buried utility services.
Road and lane closures
To be able to carry out these inspections safely and effectively, we will need to put in place the following traffic management:
• 13 December a road closure on a section of Mainstream Way
• 14 December – 15 December lane closures on a section of A47 Heartlands Parkway
• 16 December a lane closure with temporary lights on a section of Arley Road.
These will be in place from 9.00pm to 5.00am. Access to properties and businesses will be maintained at all times.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]