Notice of ground investigation and earthworks – Gilson, nr Coleshill

Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Prog-works-16-03/05/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Gilson
Contractor
BBV JV
Type of works
Earth works, Ground investigations
Estimated Start Date
15/03/2022
Estimated End Date
30/06/2022

What we are doing

In March 2022, BBV begin works in areas to the north of Gilson Road. The works will initially include us setting up site and delivering machinery. Following this we will conduct ground investigation works,
utility diversions and haul route construction works. The haul route works will involve excavating, topsoil stripping and the creation of internal haul roads.
We will access our works from Gilson Road, as identified on the map in the notification. Our working hours will be 8.00am – 6.00pm Monday to Friday and 8.00am – 1.00pm on Saturday.