Notice of ground investigation survey work near Bar Hill Road
Work item: HS2-EW-BBV-Ph1-Ar-No-N2-Prog-works-8-05/11/2021
Work Item Summary
- Project Phase
- Phase 2a
- Region
- West Midlands
- Location
- Bar Hill Road
- Worksite Name
- A525 Barr Hill Road
- Contractor
- Balfour Beatty
- Type of works
- Ground investigations
- Estimated Start Date
- 06/12/2021
- Estimated End Date
- 10/01/2022
What we are doing
We’re carrying out ground investigation work to help us better understand the ground conditions along the route. This will help to
inform the detailed design of the railway. To do this, we will use techniques including the drilling of boreholes and trial pits. We are
carrying out this work near Bar Hill Road. To carry out the work, we will use some heavy goods vehicles as well as light goods vehicles,
such as tractors and telehandlers.
How we will reduce disruption
We will keep construction traffic to a minimum, wherever possible. To reduce impact on your journeys, we will avoid travelling at peak times during the day. We will also keep our sites secure at all times.
Update: Temporary traffic lights on Bar Hill Road 6 to 21 December 2021, then 5 to 26 January 2022.
Download information relating to these works
- Notice of ground investigation survey work near Bar Hill Road
- Update: Notice of ground investigation survey work near Bar Hill Road
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]