Work item: HS2 MW BBV Ph2b Ar MA02 Gr Set 1 07/08/2021

Work Item Summary

Project Phase
Phase 2b
Region
Cheshire, North West
Location
Middlewich
Contractor
Balfour Beatty
Type of works
Ground investigations
Estimated Start Date
26/07/2021
Estimated End Date
29/10/2021

What we are doing

High Speed Two (HS2) is the new high speed railway for Britain. Balfour Beatty and its appointed subcontractors are working on behalf of HS2 Ltd to carry out the next phase of ground investigations work on the western leg of Phase 2b of HS2.

Ground investigations works are being carried out to help us better understand the ground conditions along the route to inform the detailed design of the railway. The ground investigation techniques that will be used on this project will primarily include the drilling of boreholes, trial pits and cone penetration tests.