Notice of ground investigations on Eton Road

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-CR-2-19/11/2021

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Adelaide Road
Worksite Name
Adelaide Road
Contractor
SCS JV
Type of works
Ground investigations
Estimated Start Date
08/12/2021
Estimated End Date
17/12/2021

What we are doing

Works planned on Eton Road from 8 December

As part of our ongoing works to set up the Adelaide Road site, we will be carrying out ground investigation works on Eton Road. This will involve digging a temporary trench to confirm the location of utility services
under the road surface. The ground investigation works will take approximately 10 days, starting from 8 December until 17 December.

We will be working during our core hours which are 8am to 6pm Monday to Friday and 8am to 1pm on Saturdays. Eton Road will be closed for the duration of these works, please see further information below.

How the trial holes might affect you
During the ground investigation works, a road closure will be in place on Eton Road to protect staff and ensure that traffic can safely move through this area. Parking bay suspensions will be in place.

The location of these works shown on a map on the following page and a clearly signed diversion route will be in place. This temporary change has been agreed with Camden Council in order to help maintain traffic flow on Adelaide Road and local streets.

Your utility services will not be affected.